Timberland factory project is built on a 40,000m2 land area with a total floor area of ​​nearly 250,000m2, including 8 towers and 1 basement. In the future, the project will be a factory for manufacturing and distributing luxury furniture for domestic and international projects.

In this project, GOCONS participates in the construction of GD1,2 structural items. The project is expected to be constructed within 10 months and will be handed over to the Investor at the end of July 2019.

GOCONS commits to ensuring quality, labor safety and supporting the Investor in the installation of machinery to put the project into operation soon. In addition, we believe that with this good start, the cooperative relationship between ALC, the General Contractor and the Investor will go further in the future.